Deferred maintenance calculator for any portfolio

See where your backlog and FCI are heading in 5 and 10 years at today's spend and at a raised level, then work out the yearly renewal budget that keeps buildings from falling behind.

  • Free, no sign-up
  • Nothing is saved

Plan your backlog and renewal budget

Two calculators: project where your backlog goes in 5 and 10 years, or work out the yearly capital renewal budget. Every rule of thumb can be changed. Dollar signs and commas are fine.

This tool serves every type of building. For schools, the school deferred maintenance calculator starts from published school capital benchmarks.

Repairs and replacements that are due but not done. For example $8,000,000.
What it would cost to replace the buildings today. For example $100,000,000.
No replacement value? Work one out from floor area

Multiply floor area by a construction cost per square foot. There is no starting figure: what a building costs to replace depends on its type, its systems and its region. Use your insurance schedule's value divided by the area, a recent estimate, or what similar buildings near you cost to build.

For example 300,000.
Your own figure for buildings like yours in your region. For example $350.
Repairs, preventive maintenance and capital renewal together, as the yearly need counts them; not utilities, cleaning or grounds. For example $1,000,000.
Rules of thumb (change any of them)
Starting figure: 2%, the low end of the 2 to 4 percent of replacement value that the National Research Council gives as a yearly maintenance and repair budget for public buildings.
Starting figure: 4%, myFacilities' own example: the 2% yearly need plus as much again toward the backlog. Change it to the level you want to test.
Starts at 0%. If some of the raised funding will pay for alterations, such as new layouts or added space, enter that part as a percent of replacement value: alterations improve buildings but don't clear the backlog.
No starting figure: construction costs rise at different rates by region and by type of building. Leave it empty to work in today's dollars.

This calculator runs only in your browser. Nothing you type is sent, saved or tracked.

Backlog projection

Your projection shows here

Backlog and FCI with today's spend and with raised funding
WhenToday's spendRaised funding

A rough projection from the starting figures (2% from the National Research Council's range, 4% myFacilities' own example); your results will differ. FCI bands as in myFacilities SMART™: under 5% Good, under 10% Fair, through 40% Poor, over 40% Critical.

Where the rules of thumb come from
  • National Research Council (1990), Committing to the Cost of Ownership: Maintenance and Repair of Public Buildings, https://www.nationalacademies.org/publications/9807, which puts yearly maintenance and repair spending for a large inventory of public buildings at 2 to 4 percent of current replacement value, a budget for keeping up with any backlog on top. The renewal need starts at the low end (2%). The raised level (4%) is myFacilities' own example, not a published figure: the yearly need plus as much again toward the backlog. Alterations start at 0%; the cost per square foot and inflation start empty.

A backlog grows when renewal falls behind

Buildings wear out a little every year. Roofs, boilers, chillers, windows and floor finishes each wear out on their own timetable, and when the money to replace them is not there that year, the work joins the deferred maintenance backlog. Nothing has to break for the backlog to grow. It is enough for renewal spending to sit below the rate at which the buildings age.

The projection follows that logic one year at a time. Each year it adds a renewal need, a percentage of the replacement value, and subtracts your spending on renewal and backlog work. Run it at today's spend and at a raised level, and the two columns show what the choice is worth in five and ten years.

Where 2% and 4% come from

The yearly need starts from a report about public buildings of every type. In Committing to the Cost of Ownership (1990), a National Research Council committee put the yearly budget for maintaining and repairing a large inventory of public buildings at 2 to 4 percent of their current replacement value. The calculator takes the low end, 2%, as the yearly need. Because the committee's figure covers maintenance and repair together, compare it with everything you spend to keep the buildings in repair: repairs, preventive maintenance and capital renewal, but not utilities, cleaning or grounds.

The report's range is for keeping up: a backlog that already exists needs money on top of the yearly need. So the raised funding level, 4%, is not a published figure. It is myFacilities' own example, the 2% need plus as much again toward the backlog, there to show what paying it down looks like. The report also says its guideline suits a large group of buildings over several years rather than one building in one year. Change any figure that your own records can improve:

  1. Renewal needRaise it above 2% for buildings that work hard, such as round-the-clock operations, labs or pools, and lower it for simple, lightly used space.
  2. AlterationsIt starts at 0%, which counts every raised dollar against the backlog. Enter a share if part of that money will go to new layouts or added space.
  3. Cost per square footIt starts empty, because one national figure would be wrong for most building types. Fill it in only if you work out the replacement value from floor area.
  4. InflationLeave it empty to stay in today's dollars, or enter the construction cost increase you plan with.

A portfolio that is slowly falling behind

Take a group of buildings worth $100,000,000 to replace, carrying a backlog of $9,000,000, with $1,200,000 a year spent on renewal and backlog work. Inflation is left empty and alterations stay at 0%.

  • Yearly renewal need: 2% of $100,000,000$2,000,000
  • Shortfall at today's spend: $2,000,000 − $1,200,000$800,000 a year
  • Backlog in 5 years at today's spend$13,000,000, FCI 13.0%
  • Backlog in 10 years at today's spend$17,000,000, FCI 17.0%
  • Raised funding, the example level: 4% of $100,000,000$4,000,000 a year
  • Backlog at raised funding$0 by year 5

At today's spend the backlog grows by $800,000 a year and the FCI moves from Fair into Poor. At the example level of 4%, the $2,000,000 a year above the yearly need goes to the backlog and clears it in five years. Most organizations end up somewhere between the two, and changing the raised funding figure shows any level you want to test.

What the columns and the budget tab tell you

  • Today's spend. What happens if nothing changes. A rising FCI here is a forecast, not yet a failure.
  • Raised funding. What a higher, steady level of renewal would buy. Set it beside the cost of the backlog it clears.
  • The capital renewal budget tab. It turns a reinvestment rate into a yearly dollar figure and, if you add today's spend, the gap between the two.
  • What it cannot see. The projection treats every dollar of need alike. It does not know that a roof due next year matters more than flooring due in year nine, or that some systems will fail early.

Turning two numbers into a plan

A projection shows the size of the problem. A plan needs the list behind it: which systems, in which buildings, in which year. That list comes from condition assessments and from asset records that carry install dates and expected lives.

In myFacilities, iFCA™ condition reviews and the history on each asset feed SMART™ capital planning, which spreads the renewal need over the years ahead and shows FCI for every building as work is done. The calculator gives you the headline for the whole portfolio; the plan shows where the next dollars should go.

Projecting the backlog in your type of organization

The projection works the same way everywhere. How fast buildings wear, and which money pays for their renewal, differ by type of organization.

  • Higher education. Project academic buildings apart from residence halls, dining and athletics when those run on their own revenue, since their renewal money comes from different budgets. Research buildings with heavy lab exhaust often need a renewal rate above 2%.
  • Government and public works. Leave roads, bridges and pipe networks out of this projection: they need their own models. Count only what the capital improvement program spends on existing buildings, because new construction does not clear any backlog.
  • Healthcare. Clinical buildings renew faster than most, because air handling, medical gas, nurse call and emergency power wear out sooner and must stay in service through every replacement. Consider a renewal need above 2% for hospitals and project medical office buildings as their own group.
  • Corporate. Include only the buildings you own, or must renew under your leases. Planned exits change the picture: there is little point projecting ten years of renewal for a site you expect to leave in three.
  • Retail and hospitality. Renovations set by brand standards replace finishes and furniture on their own cycle; leave that spend out of the funding figure unless it also renews roofs, HVAC, plumbing or electrical. Count managed properties only where your company makes the capital decision.
  • Sports and recreation. Pools, ice plants, turf and field lighting wear out much faster than buildings. Project them as a separate group with a higher renewal need, or the portfolio average will hide them.
  • Fire and police stations. Stations run day and night, so generators, apparatus bay doors, exhaust removal and HVAC log far more hours than an office's. A renewal need above 2% suits older stations; keep vehicles and equipment out of the replacement value.
  • Industrial and manufacturing. Separate the building shell and its services from process lines, which are renewed from operating budgets on their own depreciation schedules. Roofs over wet or hot processes and plant utilities often age faster than the shell suggests.
  • Religious organizations. Many congregations and organizations pay for repairs from a building reserve or a capital campaign; enter what actually goes to repairs and replacements in a typical year. Slate roofs, decorative glass and masonry cost more to renew like for like, so their backlog grows faster.

Worked examples. One for each type of organization, with its own numbers.

  • Higher education: A campus with $76,000,000 of deferred work

    • Backlog today, $850,000,000 to replace$76,000,000, FCI 8.9%
    • Spent a year on renewal and backlog$14,000,000
    • Renewal rate, then raised funding (% of replacement value)2.5% and 4%
    • Of the raised funding, alterations (% of replacement value)0.5%
    • Inflation a year3%
    • Backlog in 5 years at today's spend$136,949,799, FCI 13.8%
    • Backlog in 10 years at today's spend$227,225,565, FCI 19.8%
    • Backlog in 5 years at raised funding$38,835,681, FCI 3.9%
    • Backlog in 10 years at raised funding$0, FCI 0%
    At today's spend of $14,000,000 a year, the campus backlog grows from $76,000,000 to $227,225,565 in 10 years with 3% inflation, and the rating slides from Fair to Poor at 19.8%. Raising renewal funding to 4% of replacement value, with 0.5% of value going to alterations, clears the backlog within the decade. Run academic buildings apart from housing and dining, which pay from their own revenue, and put the two paths to trustees as a choice between one larger budget line now and a much larger bill later.
  • Government and public works: An agency's buildings at today's funding and at 3.5%

    • Backlog today, $140,000,000 to replace$11,500,000, FCI 8.2%
    • Spent a year on renewal and backlog$2,100,000
    • Renewal rate, then raised funding (% of replacement value)2% and 3.5%
    • Backlog in 5 years at today's spend$15,000,000, FCI 10.7%
    • Backlog in 10 years at today's spend$18,500,000, FCI 13.2%
    • Backlog in 5 years at raised funding$1,000,000, FCI 0.7%
    • Backlog in 10 years at raised funding$0, FCI 0%
    The agency spends $2,100,000 a year on its buildings, less than the 2% of value that wears out each year, so the backlog climbs from $11,500,000 to $18,500,000 in 10 years and the rating drops to Poor. At 3.5% of value, about $4,900,000 a year, the backlog falls to $1,000,000 by year 5 and is gone by year 10. Put both lines in the capital improvement plan so the council sees the cost of waiting, and count only existing buildings, not new construction.
  • Healthcare: A hospital system planning ten years of renewal

    • Backlog today, $420,000,000 to replace$31,000,000, FCI 7.3%
    • Spent a year on renewal and backlog$9,800,000
    • Renewal rate, then raised funding (% of replacement value)3% and 4.5%
    • Of the raised funding, alterations (% of replacement value)1%
    • Inflation a year3.5%
    • Backlog in 5 years at today's spend$59,090,347, FCI 11.8%
    • Backlog in 10 years at today's spend$106,496,352, FCI 17.9%
    • Backlog in 5 years at raised funding$24,347,569, FCI 4.8%
    • Backlog in 10 years at raised funding$14,105,988, FCI 2.3%
    Clinical buildings wear out faster than most, so this projection uses a renewal need of 3% a year. At the current $9,800,000, the backlog of $31,000,000 would reach $106,496,352 in 10 years with 3.5% inflation, rating Poor at 17.9%. At 4.5% of value, with 1% of value spent on alterations, it falls to $14,105,988 and rates Good at 2.3%. Present the gap as risk to patients as well as dollars: an aging air handler over a surgical suite affects infection control and scheduling, not only the hospital budget.
  • Corporate: Owned offices in a corporate portfolio

    • Backlog today, $64,000,000 to replace$4,100,000, FCI 6.4%
    • Spent a year on renewal and backlog$1,050,000
    • Renewal rate, then raised funding (% of replacement value)2% and 3%
    • Of the raised funding, alterations (% of replacement value)0.5%
    • Backlog in 5 years at today's spend$5,250,000, FCI 8.2%
    • Backlog in 10 years at today's spend$6,400,000, FCI 10.0%
    • Backlog in 5 years at raised funding$2,500,000, FCI 3.9%
    • Backlog in 10 years at raised funding$900,000, FCI 1.4%
    These owned office buildings carry $4,100,000 of deferred work. Spending $1,050,000 a year, below the 2% renewal need, lets the backlog reach $6,400,000 and cross into Poor by year 10. At 3% of value, with 0.5% kept for fit-out changes, it drops to $900,000. The real question is which sites the organization will keep: there is little sense funding ten years of renewal for an office you plan to leave, so match the projection to lease and real estate plans before asking for more.
  • Retail and hospitality: A store chain with $7,200,000 of deferred work

    • Backlog today, $96,000,000 to replace$7,200,000, FCI 7.5%
    • Spent a year on renewal and backlog$1,450,000
    • Renewal rate, then raised funding (% of replacement value)2% and 3.5%
    • Inflation a year2.5%
    • Backlog in 5 years at today's spend$11,385,982, FCI 10.4%
    • Backlog in 10 years at today's spend$17,549,328, FCI 14.2%
    • Backlog in 5 years at raised funding$0, FCI 0%
    • Backlog in 10 years at raised funding$0, FCI 0%
    The company spends $1,450,000 a year on roofs, HVAC, plumbing and electrical across its stores, well under the 2% of value they lose each year. With 2.5% inflation, the backlog grows from $7,200,000 to $17,549,328 in 10 years and every location drifts toward Poor. At 3.5% of value the backlog is cleared within five years. Keep brand refreshes of fixtures and decor out of this budget, then rank locations by their own figures so the oldest roofs and rooftop units are funded first.
  • Sports and recreation: Pools, rinks and fields at a higher renewal rate

    • Backlog today, $72,000,000 to replace$6,800,000, FCI 9.4%
    • Spent a year on renewal and backlog$1,300,000
    • Renewal rate, then raised funding (% of replacement value)3.5% and 5%
    • Backlog in 5 years at today's spend$12,900,000, FCI 17.9%
    • Backlog in 10 years at today's spend$19,000,000, FCI 26.3%
    • Backlog in 5 years at raised funding$1,400,000, FCI 1.9%
    • Backlog in 10 years at raised funding$0, FCI 0%
    Because pools, ice plants and field lighting wear out fast, this projection uses a renewal need of 3.5% a year. Against that, $1,300,000 of yearly funding falls well short, and the backlog nearly triples from $6,800,000 to $19,000,000 in 10 years, reaching 26.3%. At 5% of value the venues clear most of it by year 5, leaving $1,400,000. Split the projection into three groups, pools and ice, fields and lighting, and buildings, so the fast-wearing group does not hide inside a healthy average.
  • Fire and police stations: Station buildings already rated Poor

    • Backlog today, $38,000,000 to replace$3,900,000, FCI 10.2%
    • Spent a year on renewal and backlog$520,000
    • Renewal rate, then raised funding (% of replacement value)2.5% and 4%
    • Inflation a year3%
    • Backlog in 5 years at today's spend$7,266,970, FCI 16.4%
    • Backlog in 10 years at today's spend$12,047,262, FCI 23.5%
    • Backlog in 5 years at raised funding$1,217,238, FCI 2.7%
    • Backlog in 10 years at raised funding$0, FCI 0%
    The department's stations start at 10.2%, already Poor, with $3,900,000 of work waiting. At $520,000 a year the backlog reaches $12,047,262 in 10 years with 3% inflation, because buildings used every shift wear at the 2.5% rate this projection assumes. Funding at 4% of value brings the figure down to 2.7% by year 5 and clears it by year 10. Leave apparatus and equipment out of the value, and present the raised option as protecting response readiness, not just the buildings.
  • Industrial and manufacturing: Plant buildings and utilities over ten years

    • Backlog today, $118,000,000 to replace$12,600,000, FCI 10.6%
    • Spent a year on renewal and backlog$2,600,000
    • Renewal rate, then raised funding (% of replacement value)2.5% and 4%
    • Of the raised funding, alterations (% of replacement value)1%
    • Backlog in 5 years at today's spend$14,350,000, FCI 12.1%
    • Backlog in 10 years at today's spend$16,100,000, FCI 13.6%
    • Backlog in 5 years at raised funding$9,650,000, FCI 8.1%
    • Backlog in 10 years at raised funding$6,700,000, FCI 5.6%
    The plant's shell and services carry $12,600,000 of backlog, 10.6% of their value. Today's $2,600,000 a year nearly keeps pace, so the backlog only creeps to $16,100,000 by year 10, but the rating stays Poor throughout. At 4% of value, with 1% going to layout changes for new production, it falls to $6,700,000, still Fair at 5.6%. Roofs over hot or wet processes, switchgear and compressed air age faster than the rest, so fund those first and tie the work to planned shutdowns to avoid extra downtime.
  • Religious organizations: A building reserve that falls short each year

    • Backlog today, $9,500,000 to replace$820,000, FCI 8.6%
    • Spent a year on renewal and backlog$95,000
    • Renewal rate, then raised funding (% of replacement value)1.5% and 2.5%
    • Backlog in 5 years at today's spend$1,057,500, FCI 11.1%
    • Backlog in 10 years at today's spend$1,295,000, FCI 13.6%
    • Backlog in 5 years at raised funding$345,000, FCI 3.6%
    • Backlog in 10 years at raised funding$0, FCI 0%
    The organization puts $95,000 a year toward repairs, well under the 1.5% of value its buildings lose each year. That gap lets the backlog grow from $820,000 to $1,295,000 over 10 years, and the rating turns Poor by year 5. Raising the reserve to 2.5% of value, about $237,500 a year, clears the backlog within the decade. A building committee can use these two lines to plan a capital campaign years ahead, instead of an urgent request to members after a roof or boiler fails.

Sources

  • National Research Council, Committing to the Cost of Ownership: Maintenance and Repair of Public Buildings (1990), https://www.nationalacademies.org/publications/9807: yearly maintenance and repair at 2 to 4 percent of current replacement value for a large inventory of public buildings (the 2% starting need), a budget for keeping up with any backlog on top.
  • The 4% raised funding level: myFacilities' own example (the yearly need plus as much again toward the backlog), not a published figure.
  • FCI bands: the ones myFacilities SMART™ uses (under 5% Good, under 10% Fair, through 40% Poor, over 40% Critical).

Questions about deferred maintenance

Short answers for the people who plan and fund building renewal.

What does the projection assume?

That buildings need a steady share of their replacement value each year, that your spend stays the same every year, and that inflation, if you add it, applies to costs and values alike. Real years are lumpier, because a large roof or chiller can land in a single year. Read the trend rather than the exact dollar figure.

Why 2% and 4%?

The 2% yearly need is the low end of the range a National Research Council committee gave for maintaining and repairing public buildings: 2 to 4 percent of current replacement value a year. The 4% raised level is myFacilities' own example, the need plus as much again toward the backlog: the report's range is for keeping up, so only money above the yearly need shrinks a backlog. Both fields can be changed, and your own records or condition data should replace them when you have them.

Why is there no starting cost per square foot?

Building types differ too much. A warehouse, an office and a hospital cost very different amounts per square foot to build, and regions differ again. Your insurance schedule, a recent estimate or recent construction nearby will be closer than any national average.

What counts as alterations?

Work that changes a building rather than renewing it: new layouts, added space, upgrades for a new use. It can be worth doing, but it does not reduce the backlog, so the calculator takes it out of the raised funding before applying the rest.

How is this different from the FCI calculator?

The FCI calculator gives today's condition from today's backlog. This tool shows where that number is heading under two funding levels, and what yearly budget would hold it steady.

Is anything I type saved or sent?

No. Everything you type stays in this browser tab: nothing is sent anywhere or stored, and closing the tab wipes it.