Deferred maintenance calculator: where is your backlog heading?

See how a school district's deferred maintenance backlog and facility condition index could move over 5 and 10 years, with today's spending and with raised funding, using published benchmarks you can change.

  • Free, no sign-up
  • Nothing is saved

Plan your backlog and renewal budget

Two calculators: project where your backlog goes in 5 and 10 years, or work out the yearly capital renewal budget. Every rule of thumb can be changed. Dollar signs and commas are fine.

For other types of buildings, use the deferred maintenance calculator for any building, with presets for other types of organization.

Repairs and replacements that are due but not done. For example $8,000,000.
What it would cost to replace the buildings today. For example $100,000,000.
No replacement value? Work one out from floor area

Multiply floor area by a construction cost per square foot. The starting figure is the 2020 national average cost of new construction, $343 per square foot, from 2021 State of Our Schools. It is a rule of thumb: costs vary by region and have changed since 2020, so use your own figure if you have one.

For example 300,000.
Rule of thumb: $343, the 2020 national average (State of Our Schools 2021). Change it to your own.
Today's yearly capital spend that replaces worn-out systems or clears the backlog. For example $1,000,000.
Rules of thumb (change any of them)
Rule of thumb: 2%, the capital renewal benchmark in State of Our Schools 2021.
Rule of thumb: 4%, the report's benchmark for capital investment: renewal, alterations and the backlog.
Rule of thumb: 1%, the report's alterations benchmark. Alterations improve buildings but don't clear the backlog.
No starting figure: we found no published national figure for school construction. Leave it empty to work in today's dollars.

This calculator runs only in your browser. Nothing you type is sent, saved or tracked.

Backlog projection

Your projection shows here

Backlog and FCI with today's spend and with raised funding
WhenToday's spendRaised funding

A rough rule of thumb based on State of Our Schools 2021; your results will differ. FCI bands as in myFacilities SMART™: under 5% Good, under 10% Fair, through 40% Poor, over 40% Critical.

Where the rules of thumb come from
  • 21st Century School Fund, International WELL Building Institute and National Council on School Facilities, 2021 State of Our Schools: America's PK-12 Public School Facilities, https://www.dpi.nc.gov/documents/schoolplanning/ncsf-2021-state-our-schools-report/download: capital renewals 2% of replacement value, alterations 1%, deferred maintenance 1%, a 4% capital investment benchmark, and maintenance and operations 3% (page 28, Table 2); $343 per square foot national average cost of new construction (page 27).
  • Cross-check: National Research Council (1990), Committing to the Cost of Ownership: Maintenance and Repair of Public Buildings, https://nap.nationalacademies.org/read/9807/page/18, which puts maintenance and repair spending at 2 to 4 percent of current replacement value and warns that an existing backlog is unlikely to be reduced at that level (pages 18 and 19).

Why a deferred maintenance backlog grows

Every building system wears out on its own schedule. Roofs, boilers, windows and flooring each reach the end of their life, and replacing them is called capital renewal. When a year's renewal work is not funded, it doesn't disappear. It joins the deferred maintenance backlog, and next year's renewal need is added on top.

That is why a backlog rarely holds still. If yearly spending is below the yearly renewal need, the gap is added to the backlog every year, and the facility condition index (FCI) climbs with it.

How the projection works

Each year the calculator adds the year's renewal need to the backlog and takes off what you spend on renewal and deferred repairs. The backlog never goes below $0. FCI is the backlog divided by the replacement value.

  • Renewal need: 2% of replacement value a year. The 2021 State of Our Schools report uses 2% for capital renewals and explains that this means a facility is “fully depreciated over 50 years”.
  • Raised funding: 4% a year. The same report uses 4% for school capital investment, made up of renewals (2%), alterations (1%) and the accumulated deferred maintenance (1%). Alterations improve buildings but don't clear the backlog, so the calculator counts 3% against it.
  • A cross-check. A 1990 National Research Council report put maintenance and repair spending at 2 to 4 percent of replacement value, and warned that an existing backlog is unlikely to be reduced by spending limited to that level.

The capital renewal budget

The Capital renewal budget tab answers a simpler question: how much would we need to reinvest each year just to keep pace? At 2% of replacement value, that is the spending that replaces everything over about 50 years. If you add today's spend, it shows the yearly gap. Closing that gap stops the backlog from growing; paying the backlog down takes more on top.

Keep this separate from the operating budget. Cleaning, grounds, routine and preventive maintenance, utilities and security come from a different budget line, which the report benchmarks at 3% of replacement value.

The limits of a rule of thumb

  • National averages. The benchmarks and the $343 per square foot figure are national, and the cost figure is from 2020. Your region and your buildings will differ.
  • Smooth, not lumpy. Real renewal needs come in large steps, such as a roof or a boiler in a given year. A flat percentage evens them out.
  • No inflation unless you add it. We found no published national figure for school construction inflation, so the field starts empty and the projection is in today's dollars.
  • Only as good as the inputs. A backlog or replacement value from an old assessment will give an old answer.

For a plan you can take to the board, replace these averages with your own asset data. Read our guide to capital and bond planning and our guide to FCI.

How myFacilities helps you get ahead of the backlog

These myFacilities tools replace national averages with your own buildings' data.

SMART™ Forecasting

Builds a multi-year forecast of repairs and replacements from your own asset ages, condition and expected life, instead of one national percentage. About SMART™.

iFCA™ condition assessment

Inspections on a phone and deficiencies with repair costs keep your backlog and FCI current for every school and building. About FCI.

Questions about the backlog

Short answers for school leaders and board members.

What is deferred maintenance?

Repairs and replacements that are due but have not been done or funded. When yearly renewal work is skipped, it is added to the backlog.

How much should a district spend on capital renewal?

State of Our Schools 2021 uses 2% of current replacement value a year as the capital renewal benchmark, and 4% for capital investment that also covers alterations and the accumulated backlog. These are rules of thumb; your own asset data gives a better answer.

Why does the raised scenario count only 3% against the backlog?

Because 1% of the report's 4% benchmark is for alterations, such as changes for education or resilience. That work improves buildings but does not clear existing deferred maintenance.

Can I add inflation?

Yes. Enter a yearly percent in the optional inflation field. The replacement value, the renewal need and the backlog then grow by that rate, while today's spend stays the same in dollars. We give no starting figure because we found no published national one.

Where does $343 per square foot come from?

It is the 2020 national average cost of new construction used in State of Our Schools 2021. Costs differ by region and have risen since, so use your own figure if you can.

Is anything I type saved or sent?

No. The calculator runs only in your browser. Nothing is sent, saved or tracked, and closing the page clears it.

Keep reading

Guides and product pages for school facilities teams.

Swap the averages for your own buildings.

If you would like to see how myFacilities forecasts the backlog from real asset data, we are happy to show you.

Pick a time and we walk you through a sample school district.