Facility condition assessment schedule for any portfolio
Spread full condition assessments evenly over a cycle, see how many buildings to assess each year, and add a quick yearly walk-through so the data never goes stale.
Plan your assessment schedule
Enter how many buildings you have. The cycle starts at 5 years, a rule of thumb from the source below; you can change it. The planner spreads the buildings as evenly as it can.
Buildings to assess each year
Your schedule shows here
Enter how many buildings you have and choose Plan assessments.
A rule of thumb for planning; your own rules may differ.
What to plan for
- Bigger or older buildings take longer to assess.
- Some systems need specialist inspections on their own schedule.
- Assessments go stale: update them as work is done.
Source of the 5-year cycleA federal agency's policy for its whole portfolio of buildings and other constructed assets.
U.S. Fish & Wildlife Service, Service Manual 372 FW 4, Assessing Condition and Documenting Costs to Correct Deficiencies (April 13, 2016), section 4.6: at least 20% of its designated assets receive a comprehensive condition assessment each year, so the whole portfolio is assessed over five years, https://www.fws.gov/policy-library/372fw4.
Yearly walk-through: the same policy, section 4.7, has field stations carry out an annual condition assessment of their constructed assets between the comprehensive ones.
Why assessments run on a cycle
A facility condition assessment goes through a building system by system, covering the roof, structure, mechanical and electrical systems, plumbing, fire protection, finishes and grounds, and lists the repairs and replacements it finds with an estimated cost for each. Those findings feed the deferred maintenance backlog, the facility condition index and the capital plan.
Assessing everything in one year is costly and leaves all the data ageing at the same pace. Spreading the work over a cycle keeps the workload and the cost level from one year to the next, and means part of the picture is always recent.
Five years, with a yearly look
No single rule covers every owner, but a five-year cycle is common. The U.S. Fish & Wildlife Service, for example, gives a comprehensive condition assessment to at least a fifth of its designated assets every year, so that its whole portfolio is covered in five years. The same policy asks field stations to look over their constructed assets every year between those full assessments.
Hence the planner's starting cycle of five years, and the option of a yearly walk-through. Change the cycle to match any rules that apply to you, your insurer's expectations or your budget.
Many owners also give their most important buildings, such as those that must stay open in an emergency, a shorter cycle, and simple storage buildings a longer one. The planner treats every building alike, so if your cycles differ, run it once for each group and add the yearly counts together.
37 buildings on a five-year cycle
Nobody assesses part of a building, so the planner hands out whole buildings, as level as the numbers allow, with any remainder going to the first years.
- Buildings to assess37
- Years in the cycle5
- Average a year: 37 ÷ 57.4
- Years 1 and 28 buildings each
- Years 3, 4 and 57 buildings each
That is a fifth of the portfolio each year. Tick the walk-through box and all 37 buildings also get a quicker look every year, so a leak or a failing unit in a building whose full assessment is three years away still shows up in time.
Balance by effort, not just by count
- Size and complexity. A large building full of systems can take as long as several small ones. Swap buildings between years so each year carries a similar load.
- Specialist inspections. Elevators, boilers, fire alarms and backflow devices usually have inspections of their own, set by code or by insurers. Keep those on their own schedules and let the assessment use their results.
- Where to start. Begin with the oldest buildings, the ones with the most repairs, or the ones due in the next capital plan.
- Capacity. If your own staff carry out the assessments, check the plan against the hours they really have once their other work is done.
Between full assessments
An assessment is a snapshot that starts to age the day it is finished. Keep the findings up to date as work is finished and equipment is swapped out, and use the yearly walk-through to catch new leaks, damage and wear.
In myFacilities, iFCA™ condition reviews run on a phone and ask one question at a time, so every building is rated the same way. Each review records findings with photos and estimated costs, the FCI trend updates daily, and SMART™ capital planning folds them into the multi-year plan.
Assessment cycles in your type of organization
Spreading assessments over a cycle works for any portfolio. Which rules apply, and when buildings can be reached, differ by type of organization.
- Schools (K-12). Some states set the cycle for schools: New York, for example, has districts survey every occupied public school building once every five years (8 NYCRR 155.4), so check your own state's rules and your board's policy. Many districts also walk every building once a year between full surveys, which the walk-through option covers.
- Higher education. Campuses often assess on a rolling cycle and report a campus-wide FCI each year; group buildings by zone so assessors cover one area at a time. Residence halls and dining buildings are easiest to assess between terms, when they stand empty.
- Government and public works. Offices, park structures and garages can each run on their own cycle, with critical buildings such as emergency operations centers assessed more often. Grant and capital funding applications often ask for recent condition data, so time assessments ahead of them.
- Healthcare. Hospitals already inspect fire and life safety features on a tight schedule, so a full condition assessment can concentrate on the remaining life and cost of building systems. Clinical buildings often warrant a shorter cycle than medical offices.
- Corporate. For leased space, assess only what the lease makes you responsible for, and time each site's assessment ahead of its renewal date. Owned headquarters and campuses fit a normal five-year cycle.
- Retail and hospitality. Chains with many similar stores can assess a sample of each prototype in depth and give the rest a lighter visit, as long as every site gets a full assessment within the cycle. Hotels often line up assessments with planned renovations.
- Sports and recreation. Stadiums, arenas, pools and park structures differ greatly in size, so balance the years by effort and assess outdoor venues in the off-season. Grandstands and other structures may also need engineering inspections on their own schedule.
- Fire and police stations. Stations are occupied around the clock, so plan each assessment with the crews to avoid getting in the way of a response. With only a few stations, assessing the oldest ones every year or two may suit better than an even spread.
- Industrial and manufacturing. Plants inspect manufacturing equipment under their own maintenance programs; the condition assessment covers buildings, roofs and site utilities. Time the assessment of manufacturing areas for planned shutdowns, when the spaces can be reached safely.
- Religious organizations. Congregations and organizations with one or two buildings can assess one group of systems each year, such as roof and walls one year and heating and electrical the next, covering the whole building within five years. Volunteers with trade experience can help, guided by a simple checklist.
Worked examples. One for each type of organization, with its own numbers.
Schools (K-12): A district surveying 52 buildings every five years
- Buildings to assess, on a 5-year cycle52
- Plus a yearly walk-throughAll 52 buildings
- 202711 buildings
- 202811 buildings
- 202910 buildings
- 203010 buildings
- 203110 buildings
- Each year10 or 11 buildings
On a 5-year cycle the district assesses 10 or 11 of its 52 buildings each year, from 2027 to 2031, plus a yearly walk-through of every building. Confirm whether the state or the school board requires a particular cycle before fixing the length. Put the oldest schools and those with portables in the first two years, plan visits around testing weeks, and use the yearly walk-through to catch roof and boiler problems early, before they turn into emergency repairs during the school year.Higher education: A 136-building campus on a four-year cycle
- Buildings to assess, on a 4-year cycle136
- Buildings your team can assess a year30
- A full round at that pace5 years
- 202734 buildings
- 202834 buildings
- 202934 buildings
- 203034 buildings
- Each year34 buildings
Covering 136 buildings in 4 years means 34 assessments a year from 2027 to 2030, but the current team can do only 30 a year, so a full round would take 5 years. Either add a consultant for the 4 extra buildings each year or accept a 5-year cycle for low-risk buildings such as storage and parking structures. Group academic buildings by zone, and assess housing and dining between terms, when rooms stand empty and access is simple.Government and public works: An agency assessing 64 buildings over six years
- Buildings to assess, on a 6-year cycle64
- Buildings your team can assess a year12
- 202611 buildings
- 202711 buildings
- 202811 buildings
- 202911 buildings
- 203010 buildings
- 203110 buildings
- Each year10 or 11 buildings
A 6-year cycle means 10 or 11 of the agency's 64 buildings each year from 2026 to 2031, and at 12 a year the in-house team keeps up with room to spare. Assess emergency operations and other critical facilities more often than garages and park shelters, and line the schedule up with grant and capital improvement deadlines, since those requests often need current condition data. Publishing the plan also shows residents and the council how the buildings are being looked after.Healthcare: Clinical buildings on a three-year cycle
- Buildings to assess, on a 3-year cycle14
- 20275 buildings
- 20285 buildings
- 20294 buildings
- Each year4 or 5 buildings
With 14 buildings on a 3-year cycle, the organization assesses 4 or 5 a year from 2027 to 2029. A short cycle suits hospital and clinic buildings, where air handling, medical gas and emergency power carry high risk; medical office buildings could move to a longer cycle and run as a separate plan. Fire and life safety items already get frequent testing, so point the assessors at the remaining life of each system and the price of renewing it.Corporate: Owned and leased sites on a five-year round
- Buildings to assess, on a 5-year cycle18
- 20284 buildings
- 20294 buildings
- 20304 buildings
- 20313 buildings
- 20323 buildings
- Each year3 or 4 buildings
Eighteen sites on a 5-year cycle means 3 or 4 assessments a year from 2028 to 2032. For leased offices, limit the scope to what the lease makes the organization responsible for, and schedule each one in the year before its renewal date, so the findings can shape the negotiation. Owned headquarters buildings fit the normal cycle. Put sites you expect to exit late in the round, or skip them, and spend the effort where you will still be in five years.Retail and hospitality: A chain of 120 stores assessed by prototype
- Buildings to assess, on a 5-year cycle120
- Buildings your team can assess a year30
- 202724 buildings
- 202824 buildings
- 202924 buildings
- 203024 buildings
- 203124 buildings
- Each year24 buildings
Assessing 120 stores over 5 years takes 24 a year from 2027 to 2031, and a capacity of 30 a year leaves room for follow-up visits. Because many stores follow a few standard layouts, inspect two or three of each layout thoroughly and give the others a lighter check, while still reaching every location once per round. Time each visit ahead of planned remodels and brand refreshes, so the findings land in those budgets instead of turning into emergency repairs.Sports and recreation: Arenas, pools and park structures on a four-year plan
- Buildings to assess, on a 4-year cycle26
- Plus a yearly walk-throughAll 26 buildings
- 20277 buildings
- 20287 buildings
- 20296 buildings
- 20306 buildings
- Each year6 or 7 buildings
With 26 venues and structures on a 4-year cycle, the organization assesses 6 or 7 a year from 2027 to 2030, plus a yearly walk-through of every one. Sizes vary widely, so balance each year by effort rather than count: one arena can take as long as several park shelters. Visit outdoor fields and pools in the off-season, and keep separate engineering inspections of grandstands on their own schedule so the two programs do not get confused.Fire and police stations: Nine stations, three assessed each year
- Buildings to assess, on a 3-year cycle9
- 20263 buildings
- 20273 buildings
- 20283 buildings
- Each year3 buildings
With 9 stations on a 3-year cycle, the department assesses 3 a year from 2026 to 2028. Stations are occupied every shift, so plan each visit with the crews and be ready to pause when a call comes in. With so few buildings, an even spread is not the only choice: the oldest stations could be assessed every year while the newer ones wait their turn. Ask assessors to look closely at bay doors, exhaust removal, generators and fuel systems.Industrial and manufacturing: A plant with 21 buildings and site structures
- Buildings to assess, on a 4-year cycle21
- Buildings your team can assess a year4
- A full round at that pace6 years
- 20286 buildings
- 20295 buildings
- 20305 buildings
- 20315 buildings
- Each year5 or 6 buildings
On a 4-year cycle the company would assess 5 or 6 of its 21 buildings a year from 2028 to 2031, but its team can manage only 4 a year, which stretches a full round to 6 years. Bring in an outside assessor for the shortfall, or put warehouses on a longer cycle. Schedule production areas for planned shutdowns, when they can be reached safely, and keep manufacturing equipment out of scope, since it follows its own maintenance program.Religious organizations: Three buildings, one full assessment each year
- Buildings to assess, on a 3-year cycle3
- Plus a yearly walk-throughAll 3 buildings
- 20271 building
- 20281 building
- 20291 building
- Each year1 building
The organization's three buildings, a main building, a social hall and an education wing, fit a 3-year cycle of 1 assessment a year from 2027 to 2029, with a yearly walk-through of all of them. Ask a qualified assessor for the full assessments, and let volunteers with trade experience help with the walk-throughs using a simple checklist. Report findings to the building committee each spring so repairs can be planned around the calendar of services and events.
Sources
- U.S. Fish & Wildlife Service, Service Manual 372 FW 4, Assessing Condition and Documenting Costs to Correct Deficiencies (April 13, 2016), https://www.fws.gov/policy-library/372fw4: a comprehensive condition assessment for at least 20% of designated assets each year so the portfolio is covered over five years (section 4.6), and annual condition assessments by field stations (section 4.7).
Questions about assessment schedules
Short answers for facilities and capital planning teams.
How often should a facility condition assessment be done?
Many owners run full assessments on a five-year cycle, with a lighter look every year. Check any rules that apply to your buildings, and your insurer's requirements, before you settle on a cycle.
How many buildings should we assess each year?
Take the number of buildings and divide it by the length of the cycle in years. On a five-year cycle that is a fifth of them a year, so 37 buildings means 7 or 8.
Where does the 5-year starting figure come from?
From the U.S. Fish & Wildlife Service's condition assessment policy (372 FW 4), which covers its whole portfolio over five years. Treat it as a starting point and enter your own cycle.
How does a walk-through differ from a full assessment?
A full assessment goes through each major system closely and puts a cost on every finding. A walk-through is a short annual visit that looks only for what has changed: new leaks, damage, or equipment that has started to struggle.
Can our own staff do the assessments?
Yes, with a consistent method: the same questions, the same rating scale and the same way of pricing findings in every building. Many owners hire consultants for complex buildings and use their own staff for the rest.
Is anything I type saved or sent?
No. Building counts and years are handled in your browser alone, with nothing passed to us or stored afterwards.
Keep going
Free calculators and product pages for condition data.
Keep condition data fresh, building by building.
We are happy to walk you through iFCA™ condition reviews and show how they would cover your own buildings.