Facilities staff time in higher education
Where campus facilities time goes, from event setups to hall turnovers
A campus team's week is split between trades shops, zones, the central plant and an academic calendar that keeps rewriting the plan. Before adding staff or cutting services, find out where the hours actually go, then move the waste into planned work.
In short
- On a campus, hours leak into walking between buildings, event setups and office moves, residence hall turnovers, and waiting for keys, parts or a lab to be cleared.
- Count two ordinary weeks in term and one peak week, by kind of time, using the time on work orders plus a short self-log for what never becomes an order.
- Compare the split with the service level your institution chose, then move reactive calls into zone windows, kitted jobs and planned turnovers.
- In myFacilities, the phone tracks time on each task, and closed work can be filtered by building, category or technician and exported for the tally.
Six places a campus week disappears
Most directors can name their busiest shop. Few know what share of a mechanic's day is spent with tools in hand. On a campus it is usually lower than expected, because work is spread across dozens of buildings with different owners and access rules.
Reactive repairs
Leaks, lights, doors and hot-and-cold calls from faculty, staff and students, each one a separate trip from the shop.
Planned work
Preventive maintenance on air handlers, pumps, elevators and central plant equipment, plus the fume hood checks research labs depend on.
Events and moves
Commencement, orientation, athletics, summer conferences and department moves that pull trades off their zones.
Turnovers
Residence hall rooms patched, painted and re-keyed in the short window between terms.
Travel
Walking or driving between the shop, the job and the parts room, sometimes three times for one repair.
Paperwork and waiting
Work control calls, departmental approvals, keys, escorts into labs, and parts that are not on the shelf.
Count it without a time-and-motion study
- Pick the weeksTwo ordinary weeks during a term and one peak week, such as move-in or commencement. A single week will mislead you.
- Start from work ordersThe time on each closed order covers repairs, planned work and most event work. Sort it by category and by zone.
- Add a short self-logFor what never becomes an order, each mechanic notes travel, waiting and errands in quarter hours, for those weeks only.
- Check it against paid hoursTotal everything and compare it with timesheets. The gap is real time too, and it usually hides in travel and waiting.
- Count the callbacksNote how many requests needed a call back to ask which building, which room or what was wrong.
What the split tells a campus director
APPA's operational guidelines describe five levels of service for maintenance, custodial and grounds. A shop that aims for planned care but logs more reactive hours than preventive maintenance is working below its chosen level, whatever the budget says.
Three readings come up often on a campus:
- Travel tops a sixth of paid hours. Zones are too wide, or parts and keys live only in the central shop.
- Spring event setups crowd out planned work. The calendar books trades time without a request, a lead time or a count.
- Waiting rivals paperwork. Lab access, key requests or departmental sign-offs slow jobs that are otherwise ready.
Example: one month for a zone shop. Made-up numbers for a team of 12 mechanics; use your own.
- Paid hours (12 mechanics × 160)1,920
- Reactive repairs610
- Planned preventive maintenance and hood checks420
- Lab, plant and building rounds180
- Event setups and moves210
- Walking and driving between buildings260
- Work control calls and paperwork120
- Waiting for parts, keys or lab access120
- Reactive calls this month240
- Calls moved into zone windows (one in four)60
- Travel and waiting saved per moved call, hours (1.2 − 0.4)0.8
- Hours freed for planned work (60 × 0.8)48
Forty-eight hours is more than one mechanic's week, every month, with no new position.
Changes that give a campus team hours back
- Zone windows. Hold non-urgent requests for a building until its zone mechanic's weekly slot, and keep emergencies on the phone.
- Parts and keys at the zone. Stock the filters, lamps, washers and lock cores each zone uses most, so a repair is one trip, not three.
- Bundled lab visits. Combine hood checks, lab exhaust fan service and open lab requests in one visit, booked with the lab manager.
- Planned turnovers. Walk residence hall rooms before students leave, list the repairs, and stage parts before the term ends.
- Events as requests. Event owners request setups like any other work, with a deadline, so trades time is planned and counted.
How myFacilities counts the hours for you
Time on every task
Technicians start and finish work on a phone, which tracks the time spent on each task, adds photos and notes, and closes the order at the job.
Requests that arrive complete
Faculty, staff and students report from any phone or a room's QR sticker, so the building and room come with the request and nobody calls back to ask.
Routing by zone
Auto Assign rules send each request to the right person by site, category or time of day, so a residence hall call reaches that zone's mechanic.
A month you can total
Filter closed work by building, category or technician, save the view, and export it to a spreadsheet for the tally.
Parts used on work orders come out of stock, so zone shelves can be set from real use. Preventive maintenance plans create work orders on schedule, and the Preventive Maintenance list shows what is due or late under one overdue rule.
Try the tools
- Maintenance backlog calculator: turn open orders and mechanic hours into weeks of work for each zone.
- Custodial staffing calculator: check cleaning workloads against floor area and the service level you chose.
Repeat the count every term
Count again each term in the same calendar weeks, so move-in compares with move-in. Between counts, watch travel as a share of paid hours and reactive hours against planned ones. If freed hours never become preventive maintenance done on time, find out where they went.
Questions campus teams ask us
Short answers about where facilities hours go on a campus.
Should event setups be charged back to departments?
That is a policy choice for your institution. Either way, record each setup as a work order with its own category, so the hours are visible when budgets are set. Many campuses find events take far more trades time than anyone assumed.
How do we count residence hall turnover time?
Treat each building's turnover as planned work, with one order per floor or per room. Total the time on those orders after the term ends, and housing has a real figure for next summer's crew.
Do fume hood tests count as planned work or as rounds?
Count them as planned work. Whether your staff or a contractor tests the hoods, often with the ANSI/ASHRAE Standard 110 method, each visit is scheduled, repeatable and tied to one asset. Log the time against each hood, so lab safety and facilities share one record.
Do central plant operators belong in the count?
Yes, as their own group. Plant rounds and readings are planned time by design, so compare the plant with itself term to term rather than with the zone shops.
More for campus facilities teams
Guides and tools for colleges and universities.
Find the hours your campus already has.
See how time on tasks, routing by zone and exportable reports work for a campus team.