Maintenance staff time in plants and warehouses
Where plant maintenance time goes, beside the line and behind the locks
In a plant, a technician's shift is split between production equipment, the building and utilities around it, and the steps that make work safe: lockout, verification and waiting for a machine to be released. Measuring those hours shows how much of the day is really wrench time.
In short
- Plant maintenance time splits into wrench time on planned and breakdown jobs, and the time around it: lockout, waiting for production to release a machine, finding parts and walking.
- Energy control under OSHA 29 CFR 1910.147 and forklift examinations under 1910.178 are required time. Plan them; never squeeze them.
- Measure one normal week on every shift, by kind of time, and compare wrench time with paid hours.
- In myFacilities, each job records its time, parts and checklist steps on a phone, so planned and breakdown hours are easy to separate.
Why wrench time is lower than it looks
A breakdown on a production line comes with pressure, yet most of its hours are not spent repairing. The technician walks to the machine, waits for the operator to reach a stopping point, applies locks, verifies zero energy, finds the part is not in the storeroom, and walks back.
Plant crews also keep the building running: compressed air, dust collection, roofs, HVAC, dock doors and lighting. That work competes with production equipment for the same people, and it is usually the first to slip.
Nine kinds of plant maintenance time
- Wrench time, planned. Preventive maintenance and planned repairs with parts ready.
- Wrench time, breakdowns. Repairs on a stopped machine or line.
- Lockout and release. Applying locks, verifying, removing them and handing the machine back.
- Waiting for production. For a changeover, the end of a batch or a supervisor's go-ahead.
- Finding parts and tools. Storeroom trips, searching and borrowing.
- Walking. Between the shop, the storeroom and the job.
- Forklift follow-up. Repairs on trucks taken out of service after an examination.
- Shutdown preparation. Planning, gathering parts and lining up contractors.
- Handover and records. Shift notes, meetings and paperwork.
Measure one normal week on every shift
- Pick a normal weekNo planned shutdown, no product launch. Cover every shift with maintenance staff on it.
- Use work orders for wrench timeTotal the time on each order, split into planned and breakdown work.
- Sample the restA supervisor notes what each technician is doing at random moments, or technicians log their own day in quarter hours.
- Reconcile with paid hoursWhatever remains is the time around the work.
- Share it with productionWaiting time is a production planning problem as much as a maintenance one.
Example: one week for a ten-person maintenance crew
Made-up numbers for a plant running two shifts; use your own.
- Paid hours (10 technicians × 40)400
- Wrench time on planned jobs96
- Wrench time on breakdowns84
- Lockout, verification and release34
- Waiting for production to free the machine38
- Finding parts and tools44
- Walking to the job and back36
- Forklift repairs after examinations22
- Shutdown preparation18
- Handover, meetings and records28
- Wrench time as a share of paid hours ((96 + 84) ÷ 400)45%
- Breakdowns this week40
- Breakdowns turned into planned, kitted jobs (one in four)10
- Parts hunting and waiting saved per job, hours (1.5 − 0.4)1.1
- Hours freed (10 × 1.1)11
Eleven hours a week is more than one technician's full shift, and wrench time rises with it. Lockout time does not shrink: it is the safety step, and it belongs inside every planned job.
Changes that give technicians hours back
- Kit planned jobsStage parts, locks and the procedure before the job starts.
- Agree windows with productionChangeovers and breaks become maintenance windows, so nobody stands at a running machine.
- Group work under one lockoutWhen a machine is locked out, finish everything on it that the records show is due.
- Stock by useKeep spares near the lines that use them most, based on what work orders consumed.
- Fix forklift findings fastSend failed examinations straight to the right technician, so trucks return to service sooner.
How myFacilities shows the time around the work
Time and parts on each job
The phone records time on each task and the parts used, which come out of stock, so each machine's real cost sits on its record.
Energy control in the checklist
Each plan's checklist carries the lockout points for that machine, so the procedure travels with the work order.
Planned work on schedule
Preventive maintenance plans create work orders when due, and the Preventive Maintenance list shows what is late under one overdue rule.
Reports for the production meeting
Filter closed work by site, category, technician or cost, and export it for the weekly review with production.
Try the tools
- Maintenance backlog calculator: turn open hours and crew size into weeks of work.
- Equipment life expectancy calculator: see which compressors, roofs and switchgear are near the end of their expected life.
Questions plant teams ask us
Short answers about technician hours in plants and warehouses.
Does lockout time count as lost time?
No. It is required safety work under 1910.147, and your company must inspect each energy control procedure at least once a year. Count it as part of the job, and cut the waiting around it instead.
How do we measure wrench time without a stopwatch on everyone?
Use work order time for the hours on the tools, and a short sample for the rest. A few dozen random observations per technician over a week give a fair picture without timing anyone all day.
Should building and utility work be counted with production equipment?
Count it in the same week but as its own category. Roofs, compressed air and HVAC keep production running too, and hiding them inside breakdown time makes their neglect harder to see.
How do forklift examinations fit into maintenance time?
Each truck is examined before it goes into service, at least once a day, and after every shift when trucks are used continuously. Maintenance time starts when a truck fails, so record those repairs on the truck, separate from the examination itself.
What if production will not release a machine?
Show the waiting hours at the next production meeting. Agreed windows at changeovers or breaks usually cost production less than an unplanned stop later, and both teams can see the numbers.
More for plant and warehouse teams
Guides and tools for manufacturing and distribution.
More wrench time, less waiting at the machine.
See how job time, parts and lockout checklists work for a plant maintenance crew and its employees.