Capital planning for local government

A capital improvement plan for public facilities that holds up at the hearing

Every year the capital improvement program goes to the council with more requests than money. When each project traces back to a building's condition, a system's age and a clear rule for ranking, the program is easier to adopt, easier to defend in public and easier to update next year.

In short

  • A capital improvement program, or CIP, is the multi-year schedule of major projects a city or county intends to fund, usually five or six years long, with the first year adopted as the capital budget.
  • The facility part of the CIP is strongest when it comes from an inventory of every building and system, rated by condition and priced at today's replacement cost.
  • In myFacilities, iFCA™ condition reviews, asset history and SMART™ capital planning keep that inventory current, so the next CIP update starts from data instead of last year's spreadsheet.

Why public facility plans are hard to keep honest

A local government owns an unusual mix of buildings: city or county hall, courts, libraries, recreation centers, senior centers, police headquarters, maintenance yards, parking structures, pump stations and treatment plants. Each belongs to a different department, each department has its own wish list, and the CIP committee has to weigh a library roof against a lift station pump with very different evidence behind each.

The process is also public. Projects are reviewed by the budget office, often by a planning commission, then debated in a hearing where residents can ask why their branch library waits another year. Elections, bond referendums and grant deadlines can move the whole program. A plan that depends on one person's memory of which boiler is worst does not survive that scrutiny.

Financial reporting adds its own expectations. Under GASB Statement No. 34, governments report capital assets, infrastructure included, in their financial statements. An agency that picks the modified approach for its infrastructure, rather than depreciating it, needs an up-to-date inventory of those assets and a full, consistent round of condition ratings no more than three years apart. Facilities teams rarely run the accounting, but the inventory they keep is often the evidence finance needs.

The inventory and its condition

Build a list of every facility the agency owns or maintains, with its department, year built, size, use and current replacement value. Break each building into roof, envelope, heating and cooling, electrical, plumbing, elevators, fire alarm and sprinklers, and accessibility features. For utility and public works sites, add the pumps, generators, controls and fleet maintenance equipment that keep service running.

Rate every building with the same scale and the same questions, then calculate its facility condition index: the dollar value of overdue repairs and replacements divided by the building's replacement value. A small branch library and a large justice center become comparable on one line. The FCI calculator does the arithmetic for one building or a whole department.

Add accessibility to the same inventory. Under the ADA Title II regulations, a public entity with 50 or more employees keeps a transition plan for structural changes needed for program access, with the barriers found, the method to fix each one, a schedule and the official responsible. Barrier removal belongs in the CIP alongside roofs and boilers, not in a separate binder.

Turn condition into a ranked program

  1. Give each system a remaining lifeStart from typical life for the system type, then adjust for its condition and repair history. A rooftop unit that has needed a compressor and a fan motor in two years is not waiting for its textbook replacement date.
  2. Score every request the same wayMany agencies use a written scoring sheet: risk to health and safety, legal mandates such as accessibility, effect on service to the public, condition, operating cost savings and outside funding. Publish the sheet, so departments know how their requests will be judged.
  3. Separate repair, renewal and new spaceKeeping a building working, replacing a worn system and adding a new facility compete for the same dollars but answer different questions. The council should see each kind on its own line.
  4. Price each project for its yearEscalate estimates to the year of construction and include design, permitting and contingency. Public bidding rules and prevailing wages, where they apply, belong in the estimate too.
  5. Match projects to fundingPay-as-you-go general funds, general obligation bonds, enterprise funds for water and sewer, grants and special sales taxes each come with their own rules and timing. A project with a grant deadline may need to move ahead of one with a higher score.
  6. Coordinate with operationsSchedule work at recreation centers outside peak season, at service counters around tax and permit deadlines, and at treatment plants when demand is lowest.

How myFacilities keeps the CIP grounded

One inventory across departments

Buildings, systems and equipment from every department sit in one inventory, seen site by site or by category when the budget office asks.

Condition from the field

iFCA™ condition reviews guide staff through each building on a phone with the same questions everywhere, and findings come back with photos and an estimated cost.

A forecast the CIP can use

SMART™ capital planning turns age, condition, expected life and replacement cost into a multi-year forecast, adjusted for inflation and ready for budget meetings.

Records for finance

Work history, condition results and replacement dates stay on each asset, so the information finance needs for capital asset reporting is not rebuilt each year.

When a project is funded, project management and work orders carry it through construction, and the replaced system's new install date and life flow back into the forecast.

Example: what flat funding does to a building portfolio. Illustrative figures; it assumes every unfunded renewal joins the backlog and leaves out inflation.

  • Current replacement value of all facilities$210,000,000
  • Average life of major building systems, years30
  • Yearly renewal needed to keep pace ($210M ÷ 30)$7,000,000
  • Yearly facility renewal in the current CIP$3,200,000
  • Yearly shortfall ($7.0M − $3.2M)$3,800,000
  • Backlog today$26,000,000
  • Backlog after five years ($26M + 5 × $3.8M)$45,000,000
  • Portfolio FCI today ($26M ÷ $210M)12.4%
  • Portfolio FCI in five years ($45M ÷ $210M)21.4%

That is the slide that explains a funding request: not one leaking roof, but a portfolio sliding from fair toward poor condition at a rate anyone can check.

Try the tools

Take the program to the manager and the council

The city or county manager and the budget director need the program in a form they can defend. Give them a summary of total need by year and department, the scoring results for every request, and the portfolio FCI under the proposed funding. For the council, lead with a short list of projects where delay carries real risk, such as a failing roof over records storage or an emergency generator at a pump station, and show what each costs if it waits.

Expect questions in public. Keep the scoring sheet, condition photos and replacement dates ready, so staff can answer a resident's question about a particular facility on the spot. Then update the inventory after each construction season, before the next budget calendar starts.

Questions public works teams ask us

Short answers about capital improvement planning for local government.

How many years should our capital improvement program cover?

Five or six years is common, with the first year adopted as the capital budget and later years shown as planned. Facility systems with long lead times, such as a courthouse chiller, may need to appear further out so design can begin in time.

How does the CIP relate to GASB Statement No. 34?

GASB 34 governs how capital assets are reported in the financial statements; the CIP decides which projects get funded. They draw on the same inventory. If your government uses the modified approach for infrastructure, keep the condition assessment results and dates where finance can find them.

Where do ADA transition plan items belong?

In the same program as other facility needs, scored on the same sheet with legal mandate as one factor. That way barrier removal moves forward on a schedule the council has adopted, rather than only when a complaint arrives.

How do we handle departments that inflate their requests?

Use one scoring sheet for everyone, require condition evidence for each request and let facilities staff verify it. Requests tied to a recorded condition review and repair history tend to be more modest and easier to rank.

Can grant-funded projects jump the line?

Sometimes they should, if the grant covers most of the cost and has a deadline. Show the trade-off openly: which higher-scoring project moves back a year, and what that delay risks.

More for public works and facilities teams

Guides and tools for cities, counties and their departments.

A capital program residents can follow.

See how condition reviews, department inventories and multi-year forecasts work for your agency.