How to plan the summer maintenance window in school buildings
Summer is short. Build the list in spring, rank it, schedule around programs and have every building ready for the first day.
Summer is the one time school buildings are mostly empty, and every department wants a piece of it. Custodians need to deep clean and refinish floors. Technicians need to catch up on preventive maintenance. Contractors need roofs, boilers and paving. Programs, camps and community groups still need space. Without a plan, the weeks run out before the work does. This post follows the window from the spring list to the first-day walk-through.
In short
- Build the needs list in spring from work orders, inspections and the capital plan.
- Rank the list by safety and by what can only happen while buildings are empty.
- Schedule around summer programs and community use, building by building.
- Catch up on preventive maintenance, walk each building before the first day and close out your records.
Build the needs list in spring
Start early, while the school year still shows you what is wrong. Pull together everything that wants summer time:
- Open and deferred work orders that could not be done with students in the building.
- Deficiencies from inspections and condition assessments.
- Projects already approved in your school capital improvement plan.
- Requests from principals and site administrators, gathered by a short spring walk-through.
- Work that needs an empty building: floors, roofing, electrical shutdowns, water shutoffs and anything noisy or dusty.
- Overdue preventive maintenance on equipment you can only shut down in summer.
Put it all in one list, with a building, a trade and a rough cost on each line. A principal's wish and a failing boiler should be sorted on the same page. In myFacilities, work orders, inspections, assets and projects share the same records, so the list can come from one place and not a pile of spreadsheets.
Rank it, then schedule around summer use
There is never enough summer for everything, so rank first. Use the same order every year so principals understand it:
- Safety and code: fire and life-safety systems, exits, security hardware and playground equipment.
- Work that stops a school from opening if it is not done, such as heating plants, leaking roofs and failed electrical equipment.
- Equipment due for service or replacement before it fails.
- Comfort, appearance and requests that can wait.
Tell each site what made the list and what did not, with a reason. A plain answer, such as "this waits until next summer because the roof comes first," keeps the trust of the people who asked. Compare the top of the list with what is funded, and cut from the bottom, not the top.
Empty is not quite empty. Summer school, sports camps, leagues, graduations, elections, community groups and rentals all use school buildings. Put every use on the same calendar as the work before you assign crews. myFacilities tracks facility rentals and community use in the same account as work orders and projects, so the schedule of who is in a building sits beside the work planned for it.
- Mark which buildings and rooms are in use each week.
- Pick a work zone in each building, such as a wing or a floor, and keep programs out of it.
- Sequence noisy, dusty and shutdown work for the weeks when a site is quiet.
- Keep exits, restrooms, power and cooling available for any program in the building.
- Plan access for contractors: keys, alarms, parking and loading areas.
The summer window is won in spring, when the list is built and the calendar is shared, not in July when the crews are already behind.
Talk to program leaders early. They can usually adjust when asked in spring. They cannot when told in June.
Run contractors and projects, and catch up on preventive maintenance
Contractors need lead time. Scope and bid the large jobs in spring, and order long-lead items such as roofing materials, switchgear and major equipment as soon as the work is awarded. Hold a start-up meeting with each contractor. Agree on a single point of contact, the work zone, access rules, the district's requirements for vendors working in school buildings and a finish date that leaves room for delays. Walk each project weekly and keep a punch list. Track each job with project management so schedule and budget stay visible in one place.
Summer is also when preventive maintenance gets caught up. Boilers, chillers, air handlers, kitchen equipment, generators and fire systems are hard to take offline in the school year. Schedule their work orders to fall due inside the window, assign them by crew and make sure each one ends with a finished checklist and readings. Our preventive maintenance plan post covers how to build the plans, and the preventive maintenance plan for schools guide covers school buildings in detail.
Get ready for the first day, then close out
In the last weeks, walk every building. Use one standard checklist so each site is checked the same way:
- Heating or cooling is running, and water and restrooms work.
- Lights, doors, locks and alarms work.
- Fire systems and elevators are tested and clear.
- Kitchens, labs, gyms and playgrounds are safe to use.
- Classrooms, floors and furniture are ready.
Walk with the principal and the head custodian. Log anything you find as a work order with a photo and an owner. If work will run past the first day, decide ahead of time what can continue with students in the building and what cannot. Isolate the work area, post notices and tell the principal. Never reopen a space whose safety systems are not working.
Then close out. Close each work order with time, parts and photos. File warranties, manuals and as-built drawings from projects in your document library. Update the asset records for replaced equipment with the new install year and expected life. Mark finished items in the capital plan and carry over what did not get done. Send each site a short summary of what was completed. See K-12 and higher education for how myFacilities supports school teams through the whole year.
Figure The summer window, step by step
- ListBuild the needs list from work orders, inspections and the capital plan.
- RankPut safety first, then work that needs an empty building.
- ScheduleFit the work around programs and community use.
- DeliverRun contractors and projects, and catch up on preventive maintenance.
- WalkCheck every building before the first day.
- Close outRecord the work, update assets and update the capital plan.
Questions school teams ask
When should planning for summer start?
In early spring at the latest, so contractors can be booked and long-lead materials ordered. Many districts keep a running list all year and refine it each term.
How do we handle work that will not finish by the first day?
Decide in advance which work can continue with students in the building. Isolate the area, post notices, log an open work order with a target date and tell the principal. Keep life-safety systems working at all times.
Can summer programs and construction share a building?
Yes, if they are separated by zone, access and schedule. Keep exits, restrooms, power and cooling clear for the program, and ask program leaders for their needs early.
What should we keep after the window closes?
The record: closed work orders with time, parts and photos, project documents, warranties and updated asset records. It makes next summer's list and the capital plan easier to build.