Deferred maintenance: how to measure it and how to explain it to leadership

Deferred maintenance is work that is needed and has been put off. Count it, sort it by consequence and explain it in terms leaders can act on.

Book a call
  • By myFacilities team
  • Published November 6, 2026
  • 6 min read

Every organization that owns buildings carries some deferred maintenance. A university has a residence hall roof that is past its expected life and leaking. A city has a library boiler that works, until it does not. A hospital has a bank of air handlers that are past their expected life and still in service. Leaders hear the phrase often and rarely see the list behind it.

In short

  • Deferred maintenance is needed work that has been put off, including systems past their life that still run.
  • Sort the backlog by consequence, not by age or price: life safety, mission, building fabric and comfort.
  • Track the backlog year over year, so that progress and new growth are both visible.
  • Show leaders what each funding choice does to next year's list, in plain words.

What counts, and the first measure

Deferred maintenance is repair and upkeep that an organization knows it needs and has not done, usually for lack of money, time or people. A patched roof, a chiller past its useful life and a set of fire doors that failed inspection and wait for funding all count. Routine work that is on schedule does not. A system with years of life left belongs in the capital plan, not in the backlog.

Each need on the list carries a place, an asset, a plain description, a cost estimate and a photo, and your own list needs one more field that matters most here: what happens if the work waits. In myFacilities, iFCA™ condition assessment records inspections and deficiencies with photos and a repair cost, and every site and building gets an FCI from the same records.

The FCI compares the cost of the backlog with the cost to replace the building. It reads as Good under 5%, Fair 5% up to 10%, Poor 10% through 40% and Critical over 40%. Our post on facility condition assessment basics explains how it is calculated and read.

Sort the backlog by consequence

A list sorted by cost or age answers the wrong question. Leaders need to know what happens if work waits. Put each need in one of four groups.

GroupExample
Life safetyA fire alarm panel that fails its tests, or backup power that cannot carry its load
MissionCooling for a lab, air handling for a procedure room, a boiler through winter
Building fabricA leaking roof, failed windows, a damaged drain
Comfort and appearanceWorn flooring, faded paint, a noisy but working fan

Life safety goes first and should not wait for a budget cycle. Follow your own policies, local codes and your insurer for interim protection. Mission items come next, because they stop the work the building exists for. Building fabric deserves more attention than its appearance suggests: water that gets in damages everything else, so a modest roof repair today can protect a mission system tomorrow. Comfort items come last.

Within a group, sort by how fast the problem grows and then by cost. Have a second person review the grouping, so the rule is shared.

Figure From backlog to decision

  1. ListGather every deferred need with its place, cost, photo and consequence.
  2. SortPut each need in a consequence group.
  3. ScoreWork out the FCI for each building.
  4. ChooseCompare funding choices and what each leaves on the list.
  5. ReportGive leaders a plain summary and update it each year.
The same records carry a deferred need from the list to a funding decision.

Track the backlog year over year

A backlog is a number that moves. Take a snapshot on the same date each year, ideally just before the budget cycle, and record the total by building and by consequence group.

Three things change the list between snapshots. Work gets done, and needs leave the list. Inspections find new needs, and systems age into the backlog. Estimates change as prices move. Record each separately, so the net change tells you something real. A list that stays the same size after a busy year of repairs can mean the buildings are aging as fast as you fix them.

Keep the closed items. A record of what was fixed, with the date and the cost, is the best proof that funding was used well. Watch the life-safety group closely, and track each building's FCI the same way, so a council or a board can see which buildings are improving and which are sliding.

What each funding choice does to next year's list

Every budget decision changes the list that opens the next year. Show leaders that effect in plain terms.

  • Fix the worst first. Life safety and mission items shrink or disappear. Fabric and comfort items keep aging, and some move up a group as water gets in. The worst buildings improve while the rest drift.
  • Finish one building. That building's list and FCI improve a great deal. The others keep climbing, so choose the one that serves the most people or carries the most risk.
  • Hold the line. Fund only what ages into the backlog. The list stays about the same size, and the risk stays where it is.
  • Defer again. Needs grow while they wait: a fabric item can become a mission item, and a mission item can become a life-safety item. Next year's list is longer and ranks higher.

Put the same needs in every option, so the comparison is fair, and say what is left over in each case. SMART™ Forecasting builds multi-year capital plans from asset ages, condition and costs, ready for budget meetings, boards and funding plans. Our post on capital planning from condition data shows how to turn a ranked list into a plan.

Give leaders a plain-language summary

Give leaders one page they can read quickly and repeat to someone else. Use four parts: what we have, what waiting costs us, what we recommend and what each choice leaves behind.

Write in consequences, not codes. "The library roof leaks into the reading room, and the boiler under it is near the end of its life" lands better than a score. Put the FCI after the story, as support, and not in the first line. Add a few photos, show the groups and show the progress made since last year, because leaders fund what they see working.

Leaders rarely fund a number, but they fund a clear risk with a clear fix and a clear price.

Avoid jargon and alarm. A university board, a city council and a hospital board each ask the same question: what could go wrong, and what do you need from us? Answer it, and offer a choice. The K-12 and higher education, government and public works and healthcare pages show how teams in those organizations use myFacilities.

Questions teams ask about deferred maintenance

How do we show progress when the backlog keeps growing?

Report what left the list, what joined it and the net change, side by side. Finished work is real progress even when aging adds more. Show the life-safety group on its own.

Should we list needs we know we cannot fund this year?

Yes. Leave them on the list with their group and the reason. A list trimmed to what is affordable hides the risk.

Who decides which consequence group a need belongs to?

Facilities proposes, and a small group that includes finance and the building's users agrees. Write the rule down and apply it the same way in every building.

How do we keep a long list readable?

Show leaders the groups and the top items in each, and keep the full list in your records.